MSME Samadhaan no longer takes new cases. Since 15 October 2025, micro and small suppliers file delayed-payment claims on the MSME ODR portal. Who can file, what to upload, and what happens next.
If you searched for "MSME Samadhaan", the process has moved. The Ministry of MSME's online dispute resolution portal went live on 27 June 2025, and from 15 October 2025 every new delayed-payment claim must be filed there. MSME Samadhaan, launched in 2017, now only carries older cases across to the new system.
The good news for a supplier waiting on money is that the new portal handles the whole claim online — filing, negotiation, conciliation and, if needed, arbitration — without a court.
You can file if all of these are true:
The unpaid principal plus statutory interest. Section 16 makes the buyer liable for compound interest with monthly rests at three times the RBI bank rate from the day payment fell due — often a large sum on an old invoice, and one that keeps growing while the buyer delays.
A settlement at the conciliation stage has the status of an arbitral award on agreed terms (Section 74, Arbitration and Conciliation Act, 1996), and an MSEFC award is enforceable like a court decree (Section 36 of that Act).
The portal suits undisputed or lightly disputed invoices. If the buyer raises a serious quality dispute or counter-claim, or the amount is large, it is worth a preliminary case assessment before filing so the claim, interest and documents are framed correctly. The MSME payment recovery page explains the wider route, and the money recovery guide covers options when you are not an MSME supplier.
No, not for a new case. From 15 October 2025, new delayed-payment applications under Section 18 of the MSMED Act, 2006 must be filed on the MSME ODR portal (odr.msme.gov.in); MSME Samadhaan now serves only to migrate and track older references.
Source: Ministry of MSME notification dated 3 October 2025
A supplier that is a micro or small enterprise with a valid Udyam Registration Number can file against a buyer who has not paid within the time allowed by Section 15 of the MSMED Act, 2006; medium enterprises cannot use this route, and registration obtained after the supply generally does not help for that supply.
Source: MSMED Act, 2006, Sections 2(n), 15 and 18
Under Section 16 of the MSMED Act, 2006, a buyer who pays late owes compound interest with monthly rests at three times the bank rate notified by the Reserve Bank of India, running from the date payment fell due under Section 15.
Source: MSMED Act, 2006, Sections 15–16
Section 18(5) of the MSMED Act, 2006 requires a reference to be decided within 90 days of the Council receiving it, but that is a statutory target; actual time depends on the state Council and whether the buyer settles at the negotiation or conciliation stage.
Source: MSMED Act, 2006, Section 18(5)
A buyer who applies to set aside an MSEFC award must first deposit 75% of the amount awarded, under Section 19 of the MSMED Act, 2006, which makes challenges purely for delay expensive.
Source: MSMED Act, 2006, Section 19
Request a preliminary discussion or case assessment to assess your situation. Share only a short, non-confidential summary; sending an enquiry does not create a lawyer-client relationship or confirm acceptance of a matter.
General information only — not legal advice.
Online Dispute Resolution uses digital platforms to run mediation, conciliation, or arbitration remotely. Learn how ODR works, where it's used in India, and how it differs from in-person ADR.
Conciliation is a process where a neutral conciliator can actively propose settlement terms, unlike mediation. Learn how it works, when it applies, and how conciliated settlements are enforced under Indian law.
Qualifying micro and small suppliers may use the MSEFC statutory conciliation-arbitration route under the MSMED Act, 2006 for delayed-payment disputes.
The MSMED Act gives qualifying micro and small suppliers statutory payment protections and a Facilitation Council route involving conciliation followed, if necessary, by arbitration.
How MSMEs can use the statutory conciliation process under the MSMED Act, 2006 to recover delayed payments — who qualifies, how to file, and what the Facilitation Council does.